ELEVATOR PROJECT

October 14, 2022 ~ The North elevator has been running up to standards so work on the South elevator can now commence.  Effective Mondy, October 17th, the South elevator will be out of commission for approximately 6 to 8 weeks.

October 3, 2022 ~ The North elevator is done!!  Both elevators will be in operation for two weeks.  After this time, if it is determined that the new elevator is functioning 100%, the South elevator will be shut down.

September 5, 2022 ~ Redoing the inside of the North elevator cab.

August 22, 2022 ~ The elevator project is moving along nicely.  The workers are currently replacing all the interior components of the workings of the North elevator.

August 1, 2022 ~ Work began today on the modernization of the elevators and it was decided to start with the North elevator first and is expected to take 4 to 6 weeks to complete.

May 13, 2022 ~ Great news!!  The Board signed a contract today with A&A Elevator Corporation to completely replace our existing elevators.  The project is expected to commence the first week of July.  The plan as of now is to start with the South elevator and should take approximately 4 to 6 weeks to complete.  When done, the North will be started, and this too should take about the same amount of time.  Stay tuned........